Realised projects

10. Vasilikos Power Station, Cyprus (2004-2005)
Putting into operation a 180 ton/h steam boiler. Erection of automated control system using equipment and software by ABB.100 % erection and participation in commissioning activities.

9. Central Heating Boiler House in Gomel (2004)
Modernization of a 70 ton/h steam boiler with a 6 MW steam generating unit. Erection of automated control system using equipment of OMRON. 100 % erection and participation in commissioning activities.

8. Bereza Power Station (2003-2004) 
Putting into operation two 25 MW gas turbine units and one 150 MW steam turbine unit. These units are fully automated with SIEMENS equipment. Automated turbine control system by SSS is used at the units. ABB’s equipment is used to control power distribution networks, generators and transformers protection. OBBOBETTERMANN’s products were used to erect cable routes.100 % erection and participation in commissioning activities.

7. 330kV substation for “ROSS” (2003) 
Erection of GECALSTOM’s automated control system and wiring.100 % erection and participation in commissioning activities.

6. Soligorsk CHPP (2002-2003) and Mogilev CHPP-2 (2003) 
Putting into operation a 6 MW combined cycle gas turbine unit, a 100 Gcal/h hot water boiler and a 25 ton/h steam boiler. The power plants are fully automated, employing Japan’s OTRON controllers and the software by WONPERWARE of the USA. 100 % erection and participation in commissioning activities

5. “Molodechno” boiler house in Molodechno (2002) 
Modernization of a 25 ton/h steam boiler, 50 Gcal/h and 100 Gcal/h hot water boilers, including erection of an additional 5 MW steam generating unit. Installation of an automated control system based on Japan’s OTRON automated control system with the software supplied by WONPERWARE of the USA.   100 % erection and participation in commissioning activities.

4. “Druzhba” oil transporting company, Novopolotsk (2000-2002) 
Upgrade of- 6kV overhead power lines from 110 kV substation to 6kV distribution station of LPDS     Polotsk (2001) / 
  - 6kV indoor distribution device, 100kV “Polotsk” substation (2000)  /   - 6kV distribution station of LPDS Polotsk, using automated control system equipment  /   of ABB (2002).   100 % erection and participation in commissioning activities

3. Minsk CHPP-5 (1999-2000) 
Putting into operation a 300 MW steam turbine of unit No.1. This is the first fully automated unit to use an automated control system created by Ukrainian research institutions. 100 % erection and participation in commissioning activities.

2. 110 кV substation for Coca-Cola in Minsk (1997)  
Erection of ABB’s automated control system and wiring. 100 % erection and participation in commissioning activities. participation in commissioning activities.

1. Orsha Power Station (1997) 
Putting into operation two 66 MW combined cycle units of 66MW, comprised of two 27 MW gas turbines and one 12 MW steam turbine using component parts of GECALSTOM. The station is fully automated. 100 % erection and participation in commissioning activities.

 