Realised projects

60. Substation of 110/10 kV "Kamennaya gorka" in Minsk (2012-2014).
Performed:  the set of construction and electrical installation works on construction of a new closed substation with field cable installation of 110 kV "Substantion "Kamennaya gorka" – Substation "Sukharevo" 3.6 km long, and "Substation "Kamennaya gorka" – Substation "Zhdanovichi" 2.9 km long.

59. Substation of 110/10 kV "Brestskaya" in Minsk (2012-2014).
Performed: the set of construction and electrical installation works on construction of a new closed substation with field cable installation of 110 kV "Substation "Brestskaya" – Substation "Kurasovshchina"2.4 km long. "Zhdanovichi"2.9 kmlong.

58. Construction of Grodnenskaya HPP on the Neman river (2011-2014).
Performed:the set of electrical installation works, instrumentation and controls works on commissioning of five turbines with total capacity of 17 MW. t="on">2.4 km long. "Zhdanovichi"2.9 kmlong.

57. Substation of 110/10 kV "Petrovshchina" in Minsk (2011-2013).
Performed: the set of construction and electrical installation works on reconstruction of substation with construction of 110 kV indoor switchgear building with gas-insulated switchgear of 110 kV manufactured by Siemens.

56. Substation of  110/10 kV "Grushevskaya" in Minsk (2011-2013).
Performed:the set of construction and electrical installation works on construction of a new closed substation with field cable installation of 110 kV "Substation "Grushevskaya" – Substation "Petrovshchina" 3.7 km long.

55. Substation of 110/10 kV "Dolginovskaya" in Minsk (2011-2012).
Performed: the set of construction and electrical installation works on construction of a new closed substation with field cable installation of 110 kV "Substation "Dolginovskaya" – Substation "Vesnyanka" 4 km long.

54. Vitebskaya CHPP (2011).
Performed: the set of electrical installation works, instrumentation and controls works on replacement of turbine unit No. 2 with a capacity of 35 MW for turbine unit with a capacity of 40 MW.100 % installation and participation in adjustment.

53. Minskaya CHPP-5 (2010-2011).
Performed: the set of construction and electrical installation works on expansion and reconstruction of 330 kV outdoor switchgear with installation of high-voltage equipment of 330 kV manufactured by АВВ, SIEMENS, TRENCH, Koncar-Instrument, ZETO.100 % installation of construction and electrical part and participation in adjustment.

52. Berezovskaya GRES (2009-2011).
Performed: set of construction and electrical installation works on construction of a new outdoor switchgear of 330 kV with installation of high-voltage equipment of 330 kV manufactured by TRENCH and SIEMENS, installation of autotransformer with a capacity of 200 MW and 110 kV and 330 kV power cables (in the Republic of Belarus this cable was installed for the first time).100 % installation of construction and electrical part and participation in adjustment.

51. 330/220/110/35 kV Substation “Miradino” of Mogilev region (2009-2011).
Performed: the set of construction and electrical installation works on construction of a new outdoor switchgear of 330 kV, dismounting of existing 110 kV outdoor switchgear and construction of a new one, dismounting of existing 220 kV outdoor switchgear and construction of a new one, installation of autotransformer with a capacity of 200 MVA. All installed high-voltage equipment of 110-330 kV is manufactured by АВВ and SIEMENS. 100 % installation of construction and electrical part and participation in adjustment.

 